நேரம் மற்றும் வேலை 5 METHODSதான் CONFIRM 1மார்க் எடுக்கலாம்!!!
1.Work =Total Time × Rate of Work
2.Rate of Work = 1 / Total Time
Time Taken for a work = 1 / Rate of Work
3.If a Work is completed in n days/hours, then the work completed on one day/hours is equal to 1/n
4.Total Work = Efficiency × Number of Days
5.If x people can do W1 work in D1 days while putting in H1 hours per day, and if x people can complete W2 work in D2 days while putting in H2 hours per day, then the relationship between them will be. M1D1H1W2 = M1D2H2W1
6.If X: Y is the ratio of the number of men needed to do a task, then Y:X is the ratio of the time it will take them to complete the task.